PSPCL seeks BBMB help to increase power generation: A.Venu Prasad

PSPCL seeks BBMB help to increase power generation: A.Venu Prasad

Kanwar Inder Singh/ royalpatiala.in

Due to paddy transplantation and hot summer season,  the power demand in the Punjab  has touched more than 13000 MW.

In order to meet the rising   power demand and making all possible efforts   to supply  8 hours scheduled power to AP consumers and uninterrupted power to other consumers in the state, Punjab state power corporation limited has requested Bhakra Beas management board   to increase power generation.

In a written communication CMD PSPCL  A Venu Prasad has requested  to   Sanjay Srivastava, Chairman, BBMB to explore the modalities to generate more power from Bhakra project and run all available units round the clock to provide relief to farmers to increase water in canal system for irrigation purpose.

CMD said that the water level of the  Bhakra reservoir is less as compared to the water available in previous years. Due to this, BBMB is not generating full power to meet the demands of agriculture sector. He said that the reservoir level in BBMB at present is 1524.60 ft against last year  level of 1581.50 ft.

PSPCL seeks BBMB help to increase power generation: A.Venu Prasad
PSPCL CMD A Venu Prasad IAS

Similarly in Pong Dam, it is 1281 ft against last year level of 1335 ft. At present, 194 lakh units of power is supplied by BBMB. PSPCL is taking power presently from :

CENTRAL SECTOR 3864 MW
PURCHASE 2195 MW
BANKING 1192 MW
SALE 0
TSPL 950 MW
NPL 1320 MW
GVK 492 MW
GGSSTP 579 MW
GHTP 844 MW
RSD 410 MW
SHANAN 110 MW
UBDC 83 MW
MUKERIAN 179 MW
ASHP 120 MW
SOLAR 398 MW
RE (BIOMASS) 74 MW
TOTAL 12810 MW

 

June 30,2021